17 January 2015

A partial wall and updates

10885255_10152477113422396_107477389146445713_n

This week got off to a slow start, due to a delay in the delivery of the bricks for the front boundary wall. The bricks were finally delivered on Thursday afternoon and some progress was made in building the wall.

The husband also contacted the kitchen company on Monday to confirm if the quote was still in order – the quote we got in October 2013. Turns out it wasn’t, and one of the very nice reps came out yesterday to requote.

The delays caused by the approval of the plans really messed with our budget considerably, and we are already about R80k over budget *eep*

I will be travelling for the next 3 weeks, so updates may be slow. Expected work to be done in the next 3 weeks includes:

  • Completion of the laundry
  • Completion of the boundary wall
  • Breaking out of the wall between the kitchen and the rest of the house
  • Installation of the new front and back doors

Project budget: R600 000

Updated projected spend: R680 000

Total spent to date: R0.00

Expected spend for the next 3 weeks: R120 000